FULL LIST: The Ibadan Electricity Distribution Company (IBEDC) has published a list of previously categorized Band A feeders, now reassigned to Bands B, C, D, or E.
In the recent release by IBEDC, the Farm Feeder supplying Obasanjo Farm has been downgraded from Band A to Band E. This alteration affects approximately 28 feeders across Oyo, Ogun, Kwara, and Osun States.
According to the list, certain areas have experienced a drastic reduction in power supply, with some dropping from 20 hours of daily electricity to zero hours. This adjustment follows the guidelines set by the Nigerian Electricity Regulatory Commission, aligning the feeders with their appropriate power allocation bands.
In a separate development, during the announcement of the April 2024 supplementary Multi-Year Tariff Order, the Federal Government declared an end to subsidies on electricity consumed by Band A customers. Consequently, these customers are now required to pay N225/KWh, while other customers continue with previous rates.
Here is a breakdown of the IBEDC Band A downgraded feeders:
- IBADAN: Bank Road 11kv Feeder – Now in Band B with 16 hours supply
- OGUN: GTB 11kv Feeder – Now in Band B with 19 hours power supply
- KWARA: Seminary 11kv Feeder – Downgraded to Band B with 16 hours power supply
- IBADAN: Ami 11KV Feeder – Downgraded to Band C with 12 hours power supply
- KWARA: Asa 11KV Feeder – Downgraded to Band C with 14 hours power supply
- OGUN: Homan 11kv Feeder – Downgraded to Band C with 14 hours power supply
- OGUN: Rite Food Quarters 11kv Feeder – Downgraded to Band C with 12 hours power supply
- KWARA: Senior Staff Qtrs F20 11kv Feeder – Downgraded to Band C with 15 hours power supply
- KWARA: SF2 New Bussa 11kv Feeder – Downgraded to Band C with 12 hours power supply
- IBADAN: State House 11kv Feeder – Downgraded to Band C with 14 hours power supply
- KWARA: Yidi 11kv Feeder – Downgraded to Band C with 14 hours power supply
- IBADAN: Dugbe Awolowo 11kv Feeder – Downgraded to Band D with 11 hours power supply
- KWARA: Government House 11kv Feeder – Downgraded to Band D with 9 hours power supply
- IBADAN: ONIREKE 11KV FEEDER – Downgraded to Band D with 10 hours power supply
- IBADAN: Oremeji 11kv Feeder – Downgraded to Band D with 8 hours power supply
- IBADAN: Anfani 11KV Feeder – Downgraded to Band E with 5 hours power supply
- KWARA: Basin 11kv Feeder – Downgraded to Band E with 7 hours power supply
- Oyo: Crown 11KV Feeder – Downgraded to Band E with 1 hour power supply
- OGUN: Farm 11KV Feeder – Downgraded to Band E with 7-hour power supply
- OSUN: Gbongan Road 11kv Feeder – Downgraded to Band E with 0-hour power supply
- OYO: Impact Radio 11KV Feeder – Downgraded to Band E with 1 hour power supply
- KWARA: Mainstream 11kv Feeder – Downgraded to Band E with 0-hour power supply
- KWARA: Muritala Mohammed 11kv Feeder – Downgraded to Band E with 6 hours power supply
- OSUN: OSUTH 11KV Feeder – Downgraded to Band E with 0-hour power supply
- IBADAN: P&G 11KV Feeder – Downgraded to Band E with 7 hours power supply
- KWARA: TAIWO 11KV FEEDER – Downgraded to Band E with 6 hours power supply
- KWARA: Tanke 11kv Feeder – Downgraded to Band E with 4 hours power supply